PROCESS OF COMPLETE TROWELING
1. REQUIREMENTS ON CONCRETE
- Ensure the proper slump of concrete is 10 + (-) 2
- Ensure the materials have same color (cement, sand, stone ...)
- The time between the vehicles which supply the concrete from 7 to 12 minutes / vehicle (depending on the construction conditions ...)
- No more than 30 minutes / vehicle to ensure the surface is unified.
Step 1: Concreting
- Supply fresh concrete to the site.
- Check coffrage floor and wire mesh before pumping concrete.
- Spread a good adhesive layer (eg Sika latex ...) on the old concrete floor after cleaning (in case of applying new concrete on old concrete).
- Scratch off, spread the material acording to the desired height.
- Take the height according to the predetermined level by the machine, laser machine.
- Check the finish directly on the concrete floor.
Step 2: Troweling for the finish
- Wait from 2h-> 3h until the concrete is drained (depending on weather).
- Use power ride-on machine to trowel the surface of the concrete.
- Spread the colour powder hardener (chapdur Green, Gray ...) by hand on concrete floor with the norm of 4kg / m2. (If required).
- Use a self-propelled trowel machine and a manual trowel machine until the floor is smoothy and glossy.
2. MAINTENANCE REQUIREMENTS
- Cover the colourless nylon or canvas after polishing the floor.
- Use a shower faucet to irrigate the entire floor during the 14-day maintenance period.
- Limit worker’ s traveling and working in the area when the floor has been smoothed out.
- The troweling proccess has been completed.
- Cut the joint floor (depth 2-> 3cm) in 02 days after, divide it acording to the design.